Most PCBA lead time quotes hide the answer inside one number. A normal order runs 5–10 working days from material kitting to shipment, assuming the BOM is complete and the design is frozen. Break it into six stages and you can audit any supplier's promise.
Under turnkey supply, off-the-shelf parts usually arrive in 1–3 days and channel parts in 3–7 days; long-lead items are counted in weeks and cannot be recovered by line speed. Under consignment, the clock starts when your material arrives. PCB fabrication is typically 2–4 days and runs in parallel.
So the first question is not "how long" but "counted from PO date or from kitting date?" The two conventions can differ by a week.
Stencil fabrication is 1–2 days (same-day possible on rush), programming and reflow profile about 0.5–1 day, both in parallel with kitting. For fine-pitch BGA at 0.25 mm, do not compress the stencil decision to save a day — you will pay it back at post-reflow inspection. Moisture-sensitive BGA/QFN also needs bake time after opening, and paste warm-up and open-time limits are fixed process time, not slack.
A proper first article checks material, polarity, joints, dimensions and function: about half a day, plus half a day to a day if the customer reviews photos remotely. If the first article fails, the line stops — so fast feedback from the customer is the cheapest schedule compression available.
Placement itself is the easiest stage to calculate: boards × placements per board ÷ daily placement capacity. A 500-placement board at 5,000 pieces is 2.5 million placements — roughly a day once scheduled. The real variable is changeovers: split one order into three variants and you pay three changeovers plus three first articles.
DIP and selective soldering typically 1–2 days. ICT/FCT depends on fixtures: with your fixture, results in a day; building fixtures on site adds 2–3 days; RF products on a test set can run by the day. Rework hides in this stage — boards flagged by AOI or X-Ray need rework, re-inspection and re-stocking, and each loop pushes shipment.
Router depaneling, visual inspection and packing 0.5–1 day; conformal coating plus cure about a day, and cure time is fixed. After OQC sampling, the order ships — which lands you back at 5–10 working days from kitting.
Ask the supplier to put five dated milestones on the quotation — kitting date, stencil date, first-article date, placement date, shipment date — instead of one total. A supplier that will commit to dates has actually run a schedule. "About ten days" usually does not survive the planning board.
IQC incoming inspection: the kitting date on the schedule starts here